How to calculate quantity of Cement and Sand in Plaster
How to calculate quantity of Cement and Sand in Plaster?
Ex:
Area of plaster = 100 ft × 100 ft
Thickness of plaster = 12mm
Step 1) find out volume of plaster:
(Need to all units that is "ft" and "mm" convert into "m" )
1000mm = 1m
So that; 12mm = 0.012m
3.28ft = 1m
So that; 100ft = 30.49m
Volume of plaster = 30.49 × 30.49 × 0.012
= 11.15 m³
Step 2) Convert plaster volume wet to dry:
Take 33%
Dry vol = 11.15 × 1.33
= 14.83 m³
Step 3) Consider wastage:
Take 5%
Total dry vol = 14.83 × 1.05
= 15.57 m³
Step 4) find out Cement and sand required:
Take;
Cement : sand
1 : 6
Cement req = 1/(1+6) × 15.57
= 2.22 m³
Need to cement in bags
(density of cement 1440 kg/m³ )
= 2.22 × 1440
= 3196.8 kg (1bag = 50 kg)
= 3196.8/50
= 63.93 bags = 64 bags
Sand req = 6/(1+6) × 15.57
= 13.34 m³ (1brass = 2.83m³)
= 13.34/2.83
= 4.7 brass
OR
= 13.34 × 35.315
= 471.1 cft (1m³ = 35.315)